Scope of application
This Installation Manual suits for the Fiber Optic Splice Closure (Hereafter abbreviated as FOSC), as the guidance of proper installation.
The scope of application is: aerial, underground, pipeline, hand-holes. The ambient temperature ranges from -40 to 65℃.
Basic structure and configuration
2.1 Dimension and capacity
Outside dimension (Height x Diameter) | 460mm×205mm |
Weight (excluding outside box) | 3000 g— 3600g |
Number of inlet/out ports | 4 pieces in general |
Diameter of fiber cable | Φ8mm~Φ36mm |
Capacity of FOSC | Bunchy:24-96 (cores), Ribbon: up to 288 (cores) |
2.2 Main components
No. | Name of components | Quantity | Usage | Remarks |
1 | FOSC cover | 1 piece | Protecting fiber cable splices in whole | Height x Diameter |
2 | Fiber optic splice tray (FOST) | Max. 4 trays (bunchy) | Fixing heat shrinkable protective sleeve and holding fibers | Suitable for: |
3 | Base | 1set | Fixing internal and external structure | |
4 | Plastic hoop | 1 set | Fixing between FOSC cover and base | |
5 | Seal fitting | 1 piece | Sealing between FOSC cover and base | |
6 | Pressure testing valve | 1 set | After inject air, it is used for pressure testing and sealing testing | Configuration as per requirement |
7 | Earthing deriving device | 1 set | Deriving metal parts of fiber cables in FOSC for earthing connection | Configuration as per requirement |
2.3 Main accessories and special tools
| No. | Name of accessories | Quantity | Usage | Remarks |
1 | Heat shrinkable protective sleeve | Protecting fiber splices | Configuration as per capacity | |
2 | Nylon tie | Fixing fiber with protective coat | Configuration as per capacity | |
3 | Heat shrinkable fixing sleeve (elliptical) | Fixing and sealing single fiber cable | Configuration as per requirement | |
4 | Heat shrinkable fixing sleeve (circular) | Fixing and sealing mass of fiber cable | Configuration as per requirement | |
5 | Branching clip | Branching fiber cables | Configuration as per requirement | |
6 | Earthing wire | 1 piece | Putting through between earthing devices | |
7 | Desiccant | 1 bag | Put into FOSC before sealing for desiccating air. | |
8 | Labeling paper | 1 piece | Labeling fibers | |
10 | Buffer tube | decided by customers | Hitched to fibers and fixed with FOST, managing buffer. | Configuration as per requirement |
11 | Aluminum foil paper | 1piece | To protect the bottom of closure and inlet/outlet tubes when heating heat shrinkable fixing sleeve with fire sprays |
Spring Optical Communication is one of the largest and best gjs-d017 fiber optical vertical joint splice closure box manufacturers and suppliers with rich experience. Welcome to buy our high quality products or wholesale our customized gjs-d017 fiber optical vertical joint splice closure box in stock with our factory. Also, free sample is also available if necessary.
Hot Tags: GJS-D017 fiber optical vertical joint splice closure box manufacturers, suppliers, factory, wholesale, customized, buy, bulk, in stock, free sample